CONTRACTOR LIEN RIGHTS

April 1, 2002

Many associations find themselves in a dispute with 
contractors because they do not comply with the Florida 
Construction Lien Law (Chapter 713, Florida Statutes – The 
Mechanic’s Lien Law). There are stories of community 
associations who have paid roofers, painters and paving 
companies all of the required funds, received release of 
liens and final release of lien, when the project was 
finished, only to receive a notice of lien from a supplier 
of materials or labor that they had never been paid from 
the contractor. This can be very expensive for the 
association as they may be paying for the same work twice! 
 
The State of Florida Construction Lien Law is a mandatory 
statewide legislation, which shall be enforced in every 
jurisdiction throughout the State. Applicants for a permit 
on a building project that exceeds $2,500 in value are 
required to provide information concerning the Owner, 
Mortgage lender and the Architect/Engineer. In addition 
the application has to have the Owners notarized signature 
affixed. 
 
A certified copy of the recorded Notice of Commencement 
must be posted and maintained, along with the permit, from 
the start of the job through the final inspection. The 
State mandates that no inspections shall be approved 
without the Notice of Commencement being posted. This 
requirement applies to all permitted work regardless of 
building valuation or funding (cash or credit) source. 
 
What to do to protect your association – For your 
protection, if you are planning to spend over $2,500 on 
building or improvements, before your start building, 
repairing or replacing, it is suggested:You consult an 
attorney regarding the Mechanics Lien Law before starting a 
major construction project. Make sure that all 
requirements for recording and posting the “Notice of 
Commencement” have been accomplished. Before making any 
payments to your contractor, you should get a sworn 
statement in writing that the contractor has paid all the 
bills for your job. 
 
If you have received a “Notice to Owner” from anyone, you 
should require your contractor to get a sworn statement 
from each such person stating that they have been paid for 
all work done on your job. This should be done before 
making any payments to your contractor. If a Mechanics 
Lien is filed against your property, consult an attorney 
immediately. 
 
The Mechanics Lien Law provides a method by which a 
contractor, subcontractor, laborer, building material 
supplier, architect, landscape architect, interior 
designer, engineer, or land surveyor may claim lien on real 
property on which they have done work, or to which they 
have furnished materials. If the lien is not satisfied, 
your property may be sold to pay the lien. 
 
What is it? A “lien” is a charge or encumbrance on real 
property (land that is improved and the improvements 
thereon, including fixtures), which must be satisfied by 
the property owner to ensure clear title. “Attachment” 
means that if a court finds a claim a lien valid, the 
owners’ property may be seized and sold to satisfy the lien 
if it is not voluntarily paid. 
 
A “Notice of Commencement” is a notice, which is filed with 
the Clerk of the Circuit Court in the county where the work 
will be performed. The notice should not be recorded 
before the construction or development mortgage is 
recorded, but must be recorded before actual construction 
begins. It contains detailed information on the property 
owner, financing arrangements, and other specifics 
regarding the construction project. If a performance bond 
is to be posted, a copy of the bond must be attached to the 
“Notice of Commencement”. 
 
The owners’ responsibility – Before any construction 
begins, and after the construction mortgage has been 
recorded, the owner should take the following steps: At the 
time application is made for a building permit, a “Notice 
of Commencement” form may be created by the Association’s 
attorney or obtained from an office supply store. Complete 
the “Notice of Commencement” form with the required 
information and retain a certified copy. 
 
After the building permit is issued, record the Notice of 
commencement with the Clerk of the Circuit Court in the 
county where the work will be performed. If a performance 
bond is to be posted, a copy of the bond must be attached 
at the time of, or prior to, recordation of the “Notice of 
Commencement”. Post the certified copy of the “Notice of 
Commencement” at the job site. There is no requirement to 
post a copy of the bond at the construction site. An 
owner’s failure to comply with these requirements could 
affect title to your property. 
 
When can a lien be filed against your property? – There are 
two instances, which can result in a lien being filed 
against your property: 1. If you fail to pay your 
contractor for work performed, your property can be subject 
to a Mechanics’ Lien filed by the contractor. 2. If a 
laborer, subcontractor, or a person supplying materials to 
your property is not paid and has given you a “Notice to 
Owner” and your contractor fails to pay laborers, 
subcontractor, or material man, they can file a Mechanics 
Lien against your property. A “Notice to Owner” is a 
written statement that gives you the name, address, and 
description of the work to be done by the subcontractor or 
material man. 
 
The steps to protect the association may seem to be very 
involved but by following the Florida Mechanics’ Lien Law, 
the association will be protected from loss and potential 
delays in having any sales/transfers take place.

 